Machine setup

Installation, leveling, electrical & pneumatic wiring, I/O check, PLC programming & debugging, trial run and production stabilization.

TypeDescription
New machinesMachines from the manufacturer, including imports from Korea, installed and commissioned in Vietnam
Relocated machinesRelocation between lines or plants, re-setup and trial run
Retrofit – upgradeMechanical, electrical and program modification of running machines

Setup steps

#StepDetails
1Site surveyLayout, power, compressed air, transport route
2Mechanical installationPositioning, leveling, module assembly
3Electrical & pneumatic wiringPower, signal and air wiring per drawings
4I/O checkSensors, actuators, safety circuits
5Programming & debuggingPLC/HMI/motion program tuning to site conditions
6Trial runDry run and load run; tact time and defect rate measurement
7Production stabilizationShift support (follow/debug) until the machine is stable
8Handover & trainingAcceptance report, operation & maintenance training

Mobilization

ItemDetails
Lead timeWithin 1 week of your request
ShiftsDay, night, Sundays and holidays to your schedule
Documents & safetyGate-pass documents; compliance with safety rules and plant regulations